Search
Home
Products & Services
Key Industries
Ham Baker Adams
CST Industries, Inc.
Company Profile
Contact Us
Service Engineers Limited
–
Key Industries
–
Water & Waste Water
–
Waste Water
Waste Water
Project:
Mangere WWTP CAASU
Client:
Watercare Services Limited
Year:
2010-2011
The project primarily involved installation of 2 large client supplied centrifuges and 7 spiral conveyor systems at New Zealand's largest Waste Water Treatment Plant at Mangere. This included design, supply and installation of sludge and polymer pumps and associated
Project:
NSWWTP De-Watering Building
Client:
Watercare Services Limited
Year:
2010
The main contract was awarded to Service Engineers Limited who subcontracted Coastline Construction Group for all civil and building work, and Current Electrical for electrical works. The majority of the contract was civil based and allowed for a new entrance
Project:
NSWWTP Pond Hydraulics
Client:
Watercare Service Limited
Year:
2010
The main contract was awarded to Service Engineers Limited who subcontracted Coastline Construction Group for all civil and building work, and Current Electrical for electrical works. The contract involoved all works required for raising the Outlet Structure of Secondary Settling
Project:
Project Hobson - Heat Exchangers
Client:
Fletcher Construction Company for Watercare Services Limited
Year:
2009
This project was a joint venture between The Fletcher Construction Company (FCC) and McConnel Dowell. Service Engineers Limited worked as a subcontractor to FCC. The main contract was to construct a 3.5km tunnel under the estuary from Hobson Bay
Project:
Army Bay WWTP Solids Thickening Upgrade Stage Two
Client:
Rodney District Council
Year:
2009
This contract included supply, fabricate, install and commission a fully operational WAS thickening facility at Army Bay WWTP. This included the supply, install and commissioning of all pipework, Gravity Belt Thickener (client supplied), pumps, valves etc. Service Engineers Limited was
Project:
NSWWTP - Sludge Thickening & Blending Upgrade
Client:
North Shore City Council
Year:
2009
Service Engineers Limited was the main contractor on the project, subcontracting the electrical work to Current Electrical and the civil/construction work to Coastline Construction Group Ltd and Contract Landscapes. The contract included supply, install and commission all pipework, tanks,
Project:
Warkworth WWTP Peak Flow upgrade
Client:
Rodney District Council
Year:
2008/9
The focus of this contract was to improve the plants ability to cope with Peak / Storm flows. The design was undertaken by Harrison Grierson. As head contractor Service Engineers contract included; installation of the Acti-flow (Veolia proprietary storm flow
Project:
Beachlands WWTP upgrade
Client:
Fulton Hogan - Munukau Water
Year:
2008
This contract covered major upgrade works to an existing airated pond system plant. It included the addition of a new inlet screen and a tertiary disc filter. The design was by Opus. Service Engineers Ltd's contract included the installation
Project:
Rosedale Stage 5 PST Upgrade
Client:
Fulton Hogan - North Shore City Council
Year:
2007/8
Service Engineers Limited has been involved in many project for the NSCC at the Rosedale site which operates an MLE treatment system. This project however, was the most sizeable undertaking to date. Our scope in the "design build" partnership arrangement
Project:
Turangi WWTP
Client:
HEB Construction - Taupo District Council
Year:
2006
This MBR plant was designed by Harrison Grierson and was largely a green fields build. Service Engineers Ltd was responsible for the installation of proprietary mechanical equipment supplied by the principal such as the MBR modules and the inlet screen.
Project:
Army Bay WWTP upgrade
Client:
Rodney District Council
Year:
2005
This project covered a major upgrade of the existing site. SKM were responsible for the overall design of the 2 new SBR's into the existing system. Service Engineers took on a design build role for the complete mechanical component
Project:
Tirau WWTP Upgrade
Client:
South Waikato District Council
Year:
2005
Service Engineers contract covered refurbishment and upgrade of existing WWTP including supply and installation of all proprietary equipment and MBR's including stainless, carbon steel, and plastic pipe work.
Project:
Rosedale WWTP Peak Flow & Gravity thickeners
Client:
Fulton Hogan - North Shore City Council
Year:
2004
Service Engineers was sub-contracted to Fulton Hogan for the complete supply and installation of all mechanical components. There were two stages to the works.Stage 1 - the Peak Flow System.Stage 2 - the Gravity Thickeners.The two gravity thickeners (
Project:
Mangere WWTP Balance of plant contract
Client:
Watercare Services Ltd
Year:
2002
Service Engineers contract covered the following; design and build of ancillary systems for the co-generation upgrade including stainless and plastic piping systems for digester and natural gas. Selection, supply and installation of Gas blowers, boilers, gas dryer, pumps, etc.
Project:
Mangere WWTP other contracts
Client:
Watercare Services Limited
Year:
2003 - 2009
Other projects completed on the Mangere site over the years: 2003 - Gas Burner upgrade. 2003 - Siloxane removal system for digester gas. 2003 - HS2 removal system. Design build of 2 large stainless steel pressure vessels. 2005 - Fairview pump station. Supply and
Project:
Rosedale WWTP Other contracts
Client:
North Shore City Council
Year:
1997 - 2009
Other projects completed on the Rosedale site over the years: 1997 - Inlet works upgrade Mechanical. 1999 - Design and Build 2 x 22m diameter floating gas holder digester covers and all associated blowers, heaters, pumps and piping. 2000 - Sludge dewatering upgrade.
Key Industries
Water & Waste Water
Petro-Chemical
Energy
Infrastructure
Construction