Army Bay WWTP Solids Thickening Upgrade Stage Two

  • Client: Rodney District Council
  • Year: 2009

This contract included the supply, fabrication, installation and commissioning of a fully operational WAS thickening facility at Army Bay WWTP, including: all pipework; a (client supplied) Gravity Belt Thickener; pumps, valve etc.  Service Engineers Limited was the main contractor for the project. Current Electrical was subcontracted for all electrical works. Civil work was subcontracted to Your Local Plumber Limited.  The project ran to schedule in line with original works contracted, but ultimately ran over schedule due to additional work that was included into the program during contruction, by the client.

 

 

 

Army Bay WWTP Solids Thickening Upgrade Stage Two - Gallery