Rosedale WWTP Other contracts

  • Client: North Shore City Council
  • Year: 1997 - 2009

Other projects completed on the Rosedale site over the years:

 

  1. 1997 - Inlet works mechanical upgrade.
  2. 1999 - Design and Build 2 x 22m diameter floating gas holder digester covers and all associated blowers, heaters, pumps and piping.
  3. 2000 - Sludge dewatering upgrade.
  4. 2002 - Digesters 1 & 2 upgrade: decommission and rebuild all plant and piping, civil and electrical.
  5. 2003 - Sludge thickening project: thickener mechanisms, piping, pumps and ventilation reticulation to new odour control system.
  6. 2004 - Supply and installation of mechanical plant for Silverfield storm water storage tank.
  7. 2005 - MLE scum plant supply and install.
  8. 2006 - Digester blower upgrade. Supply and fit new blowers to increase supply to gas engines.
  9. 2006 - Gas engine exhaust supply and fit.

 

 